City of Northfield 5th Street Parking Lot


City of Northfield

5th and Water Street Preliminary Project Timeline

  • PHASE 1: COMMUNITY INPUT AND DESIGN DEVELOPMENT
  • Kick-off and Program Confirmation Meeting: October 11, 2007

    Order Feasibility Report: November 5, 2007

    Neighborhood Meeting: November 6, 2007

    Street Streetscape Conceptual Design and Water Street Parking Lot Promenade Refinements: October 23rd – Nov 16th, 2007

    Define Type and Character of Streetscape Elements: November 23rd – Dec. 6th, 2007

    Mayor’s Downtown Streetscape Task Force Presentation: December 5, 2007

    Open House: December 18-20th, 2007

    Design Development Documents: December 14th – Jan. 4th, 2007

  • PHASE 2: CONSTRUCTION DOCUMENTS AND BIDDING
  • Mayor’s Downtown Streetscape Task Force Presentation: January 9th or 10th, 2008

    Construction Documents: January 10, 2008

    Open House: January 21-24th, 2008

    Meetings with City Staff: January 21-24th, 2008

    Cost Estimates: January 23, 2008

    Project manual and Technical Specifications: February, 2008

    Receive Feasibility Report & Call For Hearing: February 4, 2008

    Mayor’s Downtown Streetscape Task Force Presentation: February 13, 2008

    Hold Public Hearing: February 19, 2008

    Prepare the Final Contract Documents: February, 2008

    City Council Presentation (Order Improvement & Preparation of P&S): March 3, 2008

    Approve Plans & Specifications: April 7, 2008

  • PHASE 3: CONSTRUCTION ADMINISTRATION AND INSPECTION
  • Open Bids: May 1, 2008

    Award Construction Contract: May 5, 2008

    Begin Construction: May 20, 2008

    Substantial Completion: November 1, 2008

    Final Completion (Wearing Course): July 1, 2009